会员体验
专利管家(专利管理)
工作空间(专利管理)
风险监控(情报监控)
数据分析(专利分析)
侵权分析(诉讼无效)
联系我们
交流群
官方交流:
QQ群: 891211   
微信请扫码    >>>
现在联系顾问~
热词
    • 1. 发明专利
    • Main beam, frame and construction method for temporary pier using them
    • 主梁,框架和施工方法使用它们
    • JP2005083179A
    • 2005-03-31
    • JP2003320253
    • 2003-09-11
    • Hanshin Kensetsu Co Ltd株式会社ハンシン建設
    • IWAI SHOZO
    • E01D21/00E01D15/133E01D15/24
    • PROBLEM TO BE SOLVED: To provide a main beam and a frame for constructing a temporary pier in a short term, and a construction method for a temporary pier using them.
      SOLUTION: First, a plurality of frames are manufactured at a factory and transported to a construction site by, for instance, a truck. At the work site, the plurality of frames is combined into a plurality of main frames 7. At their installation site, these main frames 7 are overhung and erected, then steel piles 3 are driven into the sea bottom where these frames are installed, and then the main frames 7 and steel piles 3 are fixed. This process is repeated to construct a temporary pier. This work method can simplify work at the upper pier structure and omit the work of measurements, etc. at the lower structure. So, a large reduction in construction period becomes possible.
      COPYRIGHT: (C)2005,JPO&NCIPI
    • 要解决的问题:提供一种用于短期建造临时码头的主梁和框架,以及使用它们的临时码头的施工方法。 解决方案:首先,在工厂制造多个框架,并通过例如卡车将其运送到施工现场。 在工作现场,将多个框架组合成多个主框架7.在它们的安装地点,这些主框架7被悬垂并竖起,然后将钢桩3驱动到安装这些框架的海底,并且 那么主框架7和钢桩3是固定的。 重复这一过程以建造临时码头。 这种工作方法可以简化上墩结构的工作,省略下层结构的测量等工作。 因此,施工期可大幅减少。 版权所有(C)2005,JPO&NCIPI
    • 4. 发明专利
    • Diameter enlarging apparatus for cable conduit
    • 电缆线直径扩大装置
    • JP2003333719A
    • 2003-11-21
    • JP2002142513
    • 2002-05-17
    • Hanshin Kensetsu Co LtdRyosei Densetsu Kk株式会社ハンシン建設菱星電設株式会社
    • FUKAI AKIRAMIYAHARA MANABUHAMANO TOMOJI
    • F16L1/024H02G1/06H02G9/06
    • PROBLEM TO BE SOLVED: To provide a diameter enlarging apparatus for a cable conduit capable of cutting/forming a hole part at a normal position with the axis of the cable conduit as the center. SOLUTION: There are provided a shaft 1 which is inserted into a cable conduit K, a disc-like cutter 3 which is attached to the tip of the shaft 1 and enlarges the cable conduit K by cutting from the side of an inner peripheral surface 45, and a near barrel-like spring guide body 6 which is free to contract/ expand in diameter and is disposed closer to a base end side than to the cutter 3 while capped over the shaft 1. The spring guide body 6 which has an outer diameter larger than the inside diameter of the inner peripheral surface 45 of the cable conduit K in free state guides the cutter 3 along the axis of the cable conduit K by constantly and resiliently energizing the inner peripheral surface 45 of the cable conduit K. COPYRIGHT: (C)2004,JPO
    • 要解决的问题:提供一种用于能够以电缆导管的轴线为中心在正常位置切割/形成孔部分的电缆导管的直径扩大装置。 解决方案:提供了一个轴1,其插入到电缆导管K中,一个盘状切割器3,其连接到轴1的尖端,并且通过从内部的侧面切割来放大电缆导管K 外周面45和近似筒状的弹簧引导体6,其可自由地收缩/扩大直径并且被设置成更靠近基端侧,同时被盖在轴1上。弹簧引导体6 具有比自由状态下的电缆导管K的内周面45的内径大的外径,通过对电缆导管K的内周面45进行恒定且弹性地通电来引导切割器3沿电缆导管K的轴线 版权所有(C)2004,JPO
    • 7. 发明专利
    • Pier and construction method thereof
    • 其构造方法及其构造方法
    • JP2006104709A
    • 2006-04-20
    • JP2004290415
    • 2004-10-01
    • Hanshin Kensetsu Co LtdShozo Iwai省三 岩井株式会社ハンシン建設
    • IWAI SHOZO
    • E02B3/06E01D15/133E01D21/00
    • PROBLEM TO BE SOLVED: To provide a pier which can be constructed in a short period of time, and a construction method of the pier.
      SOLUTION: Firstly, an abutment 7 is constructed on one bank, and three main girders 4a about twice longer than a span are elongated in a river crossing direction from the abutment 7 in such a manner that the abutment 7 serves as a base point. Next, a material guiding girder 2a is temporarily held in the central section of the main girder 4a (refer to Fig. 6(a)). Subsequently, after the temporarily held girder 2a is fixed, a material guiding girder 2b is temporarily held at the leading end of the main girder 4a, and fixed. Two main girders 4b about twice longer than the span are further elongated in the river crossing direction from the girder 2a in such a manner as to lay astride the girder 2b. A material guiding girder 2c is temporarily held at the leading end of the main girder 4b (refer to Fig. 6(c)). After that, the above operations are repeated. This enables the pier to be constructed in a short period of time.
      COPYRIGHT: (C)2006,JPO&NCIPI
    • 要解决的问题:提供可以在短时间内构造的码头和码头的施工方法。 解决方案:首先,将一个支座7构造在一个堤岸上,并且三个主跨梁4a大约比跨度大两倍的长度从桥接件7沿河流方向伸长,使得支座7用作底座 点。 接下来,材料引导梁2a临时保持在主梁4a的中心部(参照图6(a))。 随后,在暂时保持的梁2a固定之后,材料导向梁2b临时保持在主梁4a的前端并固定。 沿着横跨两段长度的两条主梁4b沿着横梁方向从大梁2a延伸,以横跨大梁2b的方式延伸。 材料导向梁2c临时保持在主梁4b的前端(参照图6(c))。 之后,重复上述操作。 这使得码头可以在短时间内建成。 版权所有(C)2006,JPO&NCIPI
    • 8. 发明专利
    • Temporary bridge pier unit and method for constructing temporary bridge pier by using the unit
    • 临时桥梁单元及使用单元构造临时桥梁的方法
    • JP2005060986A
    • 2005-03-10
    • JP2003290628
    • 2003-08-08
    • Hanshin Kensetsu Co Ltd株式会社ハンシン建設
    • IWAI SHOZO
    • E01D19/02E01D21/00
    • PROBLEM TO BE SOLVED: To provide a temporary bridge pier unit which enables a temporary pier to be constructed in an extremely short period of time, and a method for constructing a temporary bridge pier by using the unit.
      SOLUTION: A plurality of tubular bodies 11, a frame 12 and a receiving bag 13 are included as a unit in the temporary bridge pier unit 1. The unit 1 is constructed by installing the unit 1 in an installation place after the temporarily constructed unit 1 is transported to the target installation place by a carrier ship. The unit 1 is installed by bringing the plurality of tubular bodies 11 into contact with the bottom of a river, stabilizing each of the tubular bodies 11 via the receiving bag 13, and fixing each of the tubular body 11 and the frame 12 together after that.
      COPYRIGHT: (C)2005,JPO&NCIPI
    • 要解决的问题:提供一种能够在极短的时间内构建临时码头的临时桥墩单元,以及通过使用该单元构造临时桥墩的方法。 解决方案:在临时桥墩单元1中,多个管体11,框架12和接收袋13作为一个单元被包括在一起。单元1通过将单元1安装在临时的桥墩单元1之后的安装位置 构造的单元1由承运船运送到目标安装地点。 通过使多个管状体11与河底接触来安装单元1,通过接收袋13稳定每个管状体11,并且在此之后将管状体11和框架12中的每一个固定在一起 。 版权所有(C)2005,JPO&NCIPI