    • 3. 发明专利
    • Concrete parts for civil and building construction work
    • 公民和建筑工程的混凝土部件
    • JPS5941515A
    • 1984-03-07
    • JP15241382
    • 1982-09-01
    • Doraafutaito Kogyo Kk
    • UTSUYAMA AKIRA
    • E01D19/12E02D5/10E02D27/01E02D27/10E02D29/00E03F3/04E03F5/04E04B1/58E04B1/61E21D11/08
    • E02D27/10
    • PURPOSE:To construct deep foundation structures, etc., in a short time by connecting panel parts fitted with metal connectors of recess-projection coupling form to the both end connecting faces of a concrete part body. CONSTITUTION:Connectors 3 are fixed to the connecting faces 2 of a concrete part body 1 through anchors 5 to form a panel part. When the concrete part 1 is connected with the other concrete part 1 on site, the connectors 3 of a recess- projection coupling form, fixed to the connecting faces 2, are coupled. Since the connectors 3 are made of a metal, the surfaces of the connectors are very slippery and therefore, they can be easily coupled. Structures, e.g., deep foundation structures, piers, tunnel, U-shape trench, etc., can thus be constructed in a short time without resorting to concreting work.
    • 目的:通过将装配有凹凸联轴器形式的金属连接器的面板部件连接到混凝土零件体的两端连接面,在短时间内构造深基础结构等。 构成:连接器3通过锚固件5固定在混凝土部件主体1的连接面2上,形成面板部。 当混凝土部件1与现场的另一个混凝土部件1连接时,固定到连接面2的凹凸联接件的连接器3相连接。 由于连接器3由金属制成,连接器的表面非常滑,因此它们可以容易地联接。 因此,可以在短时间内构造例如深基础结构,墩,隧道,U形沟等的结构,而无需采用混凝土工程。
    • 4. 发明专利
    • Foundation work of structure
    • 基金会结构工作
    • JPS58204227A
    • 1983-11-28
    • JP8747082
    • 1982-05-24
    • Tokyo Electric Power Co Inc:TheTomoegumi Iron Works LtdYoshiaki Yoshimi
    • YOSHIMI YOSHIAKIKONNO KENJITAKAHASHI HIDEYOSHI
    • E02D27/32E02D27/10E02D27/42
    • E02D27/10
    • PURPOSE:To effectively utilize excavated soil by a method in which usual concrete is placed to the bottom of an excavated pit to form the bottom of foundation to fix steel skeletons, and a concrete mixed with soil generated at the site as aggregate is placed around the steel skeletons. CONSTITUTION:Usual concrete is placed to the bottom reinforced with iron bars of an excavated pit 1 to form the bottom of foundation. Also, steel skeletons 2 are hung down into the excavated pit 1, the fixing part 21 is set on the lower part 31 of the foundation bottom, and concrete is placed until the fixing part 21 is buried to form the upper part 32 of the foundation bottom. In forming the excavated pit 1 on the foundation bottom 3, the aggregate is selected from the excavated soil and packed on the foundation bottom 3 and then cement mortar is poured by a prepacked concrete method to form the intermediate portion 4 of the bottom. Then, the ordinary concrete is placed on the foundation intermediate portion 4 to form the bottom 5 of the foundation. Thus, the foundation of a structure is completed.
    • 目的:为了有效利用挖掘土壤,采用通常的混凝土置于挖掘坑底部,形成基础底部以固定钢骨架,并将与现场生产的土壤混合在一起,混凝土围绕 钢骨架。 构成:通常的混凝土被放置在底部用挖掘坑1的铁杆加固以形成基础的底部。 此外,将钢骨架2悬挂在挖掘坑1中,将固定部21设置在基础底部的下部31上,并且将混凝土放置直到固定部21被埋入以形成基础的上部32 底部。 在基础底部3上形成挖掘坑1时,从挖掘的土壤中选择骨料并将其包装在基础底部3上,然后通过预先包装的混凝土方法浇注水泥砂浆以形成底部的中间部分4。 然后,将普通混凝土放置在基础中间部分4上以形成基础的底部5。 因此,结构的基础已经完成。
    • 7. 发明专利
    • Perforated prestressed concrete base pillar
    • 执行预制混凝土基础支柱
    • JPS58185829A
    • 1983-10-29
    • JP6847382
    • 1982-04-23
    • Dainichi Concrete Kogyo Kk
    • SASA KAZUICHI
    • E04H17/22E02D27/10E02D27/32E04H12/16
    • E02D27/10
    • PURPOSE:To attain the reduction of construction cost and the enhancement of the verticality of the upper pillar by a method in which PC steel bars are symmetrically set on both side walls in the axial direction and holes or recessions are provided in the wall in crosswise direction. CONSTITUTION:An upper pillar-fitting base 5 is provided at the upper part of a perforated PC base pillar 1, a proper number of holes 2 are provided in the lower part of the pillar 1, and plural PC steel bars 6 whose basal portions are fitted with a collar nut 8 are vertically thrust into both walls 3. Also, the PC steel bars 6 are connected additionally and reinforced with a netted iron bar 9 and iron bars 9' to make up a structure having a great resistance to both bending and vertical loads. The structure is buried in a place where the cavities holes 2 can be used drain ditches, the bottom plate 15 of the upper pillar is inserted into the PC steel bar 6 for inducing prestress, and the pillar is vertically erected with a tapered nut 17 and a regulating bolt 18. Furthermore, the steel surface of the bottom plate 15 is coated with cement mortar 19 for rust-proofing treatment.
    • 目的:通过PC钢筋在轴向方向对称设置两个侧壁的方法来实现施工成本的降低和上柱的垂直度的提高,并且在壁的横向上设置有孔或凹部 。 构成:在多孔PC基柱1的上部设置有上支柱基座5,在支柱1的下部设有适当数量的孔2,多个PC钢棒6的基部为 安装有螺母8的两个壁3垂直地推入两个壁3中。此外,PC钢筋6另外连接并用网状铁棒9和铁棒9'加强,以构成对弯曲和弯曲都具有很大阻力的结构 垂直载荷 将该结构埋设在空洞2可以使用的沟渠的地方,上柱的底板15插入到PC钢筋6中用于诱发预应力,并且柱子用锥形螺母17垂直竖立, 调节螺栓18.此外,底板15的钢表面涂覆有用于防锈处理的水泥砂浆19。
    • 8. 发明专利
    • Energy-saving construction for deep foundation
    • 节能基础建设
    • JPS6128627A
    • 1986-02-08
    • JP15043684
    • 1984-07-19
    • Toshio HainoMasaaki Uchida
    • UCHIDA MASAAKIHAINO TOSHIO
    • E02D17/06E02D27/10E02D27/18E02D27/32E02D27/42
    • E02D27/10
    • PURPOSE:To improve the efficiency of work, by a method wherein after a ring frame structure is organized with a shaft core of a supporting rod fixed in ground and the tip of the structure is thrust into ground by a jack via a pressure receiver, ground is excavated by a bit fitted on the structure. CONSTITUTION:After a supporting rod 10 is fixed in the ground, a ring frame structure 12 is organized with a central shaft of the rod 10 portion exposed on the ground. Then, a pressure receiver 16 is held by the rod 10, and the lower face of the pressure receiver 16 is pressed by a jack 14, and the lower end section 13 of the structure 12 is thrust in ground. Then, a rotary shearing device 15 is worked for excavation and a retaining frame 7 is organized, and excavated earth is discharged by using a bucket 4. And after the pressure of the jack 14 is released and the pressure receiver 16 is held downward, eafth is excavated to a specified depth in the same way.
    • 目的:为了提高工作效率,通过一种方法,其中在环形框架结构以固定在地面中的支撑杆的轴芯组织并且结构的尖端通过压力承受器由千斤顶推入地面之后,地面 被挖出了一点点安装在结构上。 构成:在将支撑杆10固定在地面中之后,环形框架结构12被组织成具有暴露在地面上的杆10部分的中心轴。 然后,压力容器16被杆10保持,压力接收器16的下表面被插座14按压,并且结构12的下端部13被推入地面。 然后,为了进行挖掘而进行旋转剪切装置15的组装,并且使用铲斗4将挖掘出的土体排出,并且在释放插座14的压力并且将压力容器16保持在下方之后, 以相同的方式挖掘到指定的深度。
    • 9. 发明专利
    • Formation work of bottom slab for increasing bearing force of foundation structure
    • 基础结构增加轴承力的底板的形成工作
    • JPS59192132A
    • 1984-10-31
    • JP6599483
    • 1983-04-13
    • Kajima Corp
    • KUBOTA MUNETAKAYAMAUCHI AKIOSUZUKI KAZUOMURAO YOSHINORI
    • E02D27/30E02D27/10
    • E02D27/10
    • PURPOSE:To obtain an artificial bottom slab integrated with the foot-protected portion by a method in which the foot-protected portion is formed by pouring cement mortar through a pipe buried in the continuous underground wall, and cement mortar is placed to the area surrounded by the underground wall through a bored hole. CONSTITUTION:Cement mortar, etc., is poured through a pipe 6 buried in a continuous underground wall 5 from the ground's surface and jetted to just below the wall 5 to form a foot-protected portion 7. Boring is then made in the area surrounded by the wall 5, and cement mortar, etc., is injected through the bore hole 8 to form a bottom slab little by little to much the same level as the foot- protected portion 7. The boring process and the cement mortar pouring process are alternately repeated to widen the area of the bottom slab to obtain an artificial bottom slab 10 integrated with the foot-protected portion 7. Afterwards, a top slab 11 is placed on the underground wall 5 and then a superstructure 12 such as bridge, etc., is constructed on the top slab 11.
    • 目的:通过一种方法获得与脚部保护部分一体化的人造底板,其中通过将埋在地下连续墙壁中的管道倾倒水泥砂浆形成脚部保护部分,并将水泥砂浆放置在被围绕的区域 由地下墙穿过一个无聊的洞。 构成:将水泥砂浆等通过埋在连续地下壁5中的管6从地面注入,并喷射到壁5的正下方,形成脚部保护部分7.然后在围绕的区域中制作镗孔 通过壁5和水泥砂浆等通过钻孔8注入,以形成与脚部保护部分7一样大小的底板。钻孔过程和水泥砂浆浇注过程是 交替重复加宽底板的面积,得到与脚部保护部分7一体化的人造底板10.然后,将顶板11放置在地下壁5上,然后将上层建筑12(如桥等) ,被构造在顶板11上。