    • 5. 发明专利
    • GUIDE PIPE FOR COMPACTION PILE
    • JPH05209409A
    • 1993-08-20
    • JP34123990
    • 1990-11-30
    • TAKENAKA KOMUTEN COTAKENAKA DOBOKU
    • KAKURAI MASAAKIYAMASHITA KIYOSHITSUCHIYA TOMIOKURITA YOSHIHIKOFUKUHARA TAKUHEI
    • E02D3/08E02D5/20E02D5/34E02D5/62
    • PURPOSE:To prevent muddy water or the like from erupting while a compaction pile is driven in by a method wherein the front end of a guide pipe is shielded watertightly with a covering material equipped with a plurality of cut grooves, and a plurality of such guide pipes are integrally attached to a reinforcing bar basket to be used for construction of a continuous underground wall. CONSTITUTION:A guide pipe 1 is constructed in such structure that the front end thereof is shielded watertightly with a cover 12. A number of cut grooves 15 are formed on the cover 12 so that the grooves extend radially from the center of the cover, and thereby breaking of the cover by driving-in of a compaction pile 2 is made easy. A reinforcing material in upside-down conical shape in 45 deg. inclination is provided to the inside of the guide pipe for making correction to centering of the compaction pile 2 easy. Then a specified number of guide pipes 1 are integrally attached to appropriate positions of a reinforcing bar basket 4 for cast-in-place concrete 3, and are inserted together with the reinforcing bar basket 4 into an excavated hole. Thereby the compaction piles 2 can be driven correctly into point ground and water accompanying excavation and underground water erupting around the compaction piles can be prevented from flowing backward.
    • 10. 发明专利
    • COMPACTION PILE SUCH AS HIGH YIELD-STRENGTH CAST-IN-PLACE CONCRETE PILE
    • JPH07189247A
    • 1995-07-28
    • JP33408393
    • 1993-12-28
    • TAKENAKA KOMUTEN COTAKENAKA DOBOKU
    • YAMASHITA KIYOSHIKAKURAI MASAAKITSUCHIYA TOMIOYAMADA TAKESHICHIYOUSOKABE MAKOTOFUKUHARA TAKUHEI
    • E02D5/34
    • PURPOSE:To construct a high yield-strength cast-in-place concrete pile having large end bearing force by forming a projection to be rotated to the upper section of the inner circumferential surface of a pile body, mounting a side face cutter and a spiral projection to the lower section of an outer circumference and installing an end cutter at a front end section protruded while penetrating the pile body. CONSTITUTION:When a compaction pile is intruded to an end ground and compacted, a connector 3 is inserted into the hollow section 5 of a pile body 1 from an upper section, and the pile body 1 is turned slightly under the state, in which the constricted sections 10 of the connector 3 are fast stuck onto the inner circumferential surface of the lower end section of the hollow section 5. Consequently, the hanging sections 9 of the connector 3 creep to the lower ends 7a of the projections 7 to be rotated of the compaction pile 1 and are brought to a caught state, and the pile body 1 is borne under a hung state. An intrusion rod is operated under such a state, and the pile body 1 is intruded into the end ground in a glass pipe in an excavated pit. When the pile body 1 is penetrated completely, the pulling-up operation of the intrusion rod is conducted while the inside of the end ground is impregnated with cement milk from a discharge opening 7 through the impregnating hole of the intrusion rod.