热词
    • 1. 发明专利
    • PILE HEAD STRUCTURE
    • JP2001073387A
    • 2001-03-21
    • JP24810299
    • 1999-09-02
    • SHIMIZU CONSTRUCTION CO LTDKUBOTA KK
    • TAKURA TAKASHIOTSUKI AKIRASATO MASAYOSHIWAKITA EIJIMANO HIDEYUKIIWAMOTO TOSHIYUKIARAKAWA NORIYUKIOKAWA MASAYUKI
    • E02D27/12E02D27/34
    • PROBLEM TO BE SOLVED: To prevent a large bending moment from occurring on a foundation pile by overlapping an upper structure side spherical member having a spherical face along the spherical face of a spherical face member on a foundation side spherical face part provided on the head part of the foundation pile, and having a proper friction resistance between the spherical faces. SOLUTION: The foundation side spherical face member 2 having a projection spherical face 2a is attached to the pile head 1a of the foundation pile 1 embedded in ground 5. The upper part structure side spherical face member 4 having the recess spherical face 4a of curvature along the projection spherical face 2a is arranged on the foundation side spherical face member 2. The proper friction resistance is carried by the contact interface of the projection spherical face 2a and the recess spherical face 4a. Thereby it is rigid connection structure in an intermediate and small-scaled earthquake, and during a large-scaled earthquake, it is the structure having a rotating function while a large bending moment is transmitted. In addition, the safety of the pile head 1a can be secured, the cross sectional force of the foundation pile 1 can be lessened, the foundation pile 1 can have the necessary minimum performance, and construction work is simplified.
    • 2. 发明专利
    • PILE FOUNDATION STRUCTURE
    • JP2001064982A
    • 2001-03-13
    • JP24234399
    • 1999-08-27
    • SHIMIZU CONSTRUCTION CO LTD
    • WAKITA EIJI
    • E02D27/12E02D27/34
    • PROBLEM TO BE SOLVED: To surely prevent the damage of a foundation pile at an earthquake by fixing an interposing member comprising an elasto-plastic material to one of a foundation building frame or a foundation pile head part, regulating horizontal mutual displacement to the other, and contacting it so that vertical mutual displacement is allowed. SOLUTION: An interposing member 13 made of a low yield point steel material or the like is fixed to the side of a pile head part 8, and is contacted alone with the inner wall 6a of an insertion hole 6. In the case where horizontal force acts on a structure, compression force acts on part of the interposing member 13 by mutually moving a foundation building frame 3 to a foundation pile 2 in the horizontal direction. In the case where an earthquake is large-scaled and stress occurring in the interposing member 13 is yield stress or more, a part exceeding the yield stress of the interposing member 13 out of inertia force generated on the foundation building frame 3 is enabled not to transmit from the foundation building frame 3 to the foundation pile 2 as push force by allowing the interposing member 13 to be the saturated state of the stress.
    • 3. 发明专利
    • PILE FOUNDATION STRUCTURE
    • JP2000178981A
    • 2000-06-27
    • JP35553498
    • 1998-12-15
    • SHIMIZU CONSTRUCTION CO LTD
    • WAKITA EIJI
    • E02D27/12E02D27/34E02D31/08
    • PROBLEM TO BE SOLVED: To provide a pile foundation structure obtained by combining a foundation skeleton and a foundation pile, which can prevent damage of the foundation pile without fail at the time of a large earthquake, and can achieve reduction of costs, based on the specifications of the piles and by decreasing the number of piles. SOLUTION: A pile foundation structure 1 is made up of a foundation skeleton 2 and a foundation pile 3 with an elastoplastic material 4 interposed at a coupling portion therebetween. The elastoplasic material 4 is provided at the coupling portion between the foundation skeleton 2 and a foundation pile head portion 7, or between the skeleton 2 and a head peripheral wall 9 of the base pile, and the coupling portion between the base body and the base pile head portion is formed into a coupling hole 5. Further, a steel member is arranged on a wall of the hole, or alternatively, a sliding plate is provided on the bottom surface of the coupling hole, and a steel plate which is in contact with the sliding plate, is arranged on the center of the foundation pile head portion. Thus, even at the time of a large or small earthquake, only a small horizontal displacement is caused in the pile foundation structure, which can prevent damage of the foundation pile without fail. Further, the specifications of the piles and decrease in the number of the piles can lead to reduction of costs.
    • 5. 发明专利
    • PILE FOOTING AND REINFORCING METHOD THEREOF
    • JP2000027196A
    • 2000-01-25
    • JP19110298
    • 1998-07-07
    • SHIMIZU CONSTRUCTION CO LTD
    • WAKITA EIJI
    • E02D5/28E02D27/12E02D33/00
    • PROBLEM TO BE SOLVED: To provide a pile footing of a building capable of executing the inspection of sound efficiency of a pile and the reinforcement of the pile during the period of using the building. SOLUTION: A pile footing is so constituted that the upper end section of a pile placed by passing through a footing slab 2 is opened. By the constitution, the inspection of sound efficiency of the pile and the reinforcement of the pile can be carried out. In the pile footing passing through the footing slab 2 to place and opening the upper end section of the pile footing, an inspection method of the pile footing can simply carry out the inspection of a state of the pile by inserting an investigation equipment from an opening 5 of the upper end of the pile 1. A reinforcing method of the pile footing can increase the strength of the pile 1 by casting reinforced concrete from the opening 5 of the upper end of the pile 1 in the pile footing passing through the footing slab 2 to place and opening the upper end section of the pile footing.
    • 9. 发明专利
    • LANDSLIDE PROTECTION WALL AND CONSTRUCTION METHOD THEREFOR
    • JP2000160559A
    • 2000-06-13
    • JP33323498
    • 1998-11-24
    • SHIMIZU CONSTRUCTION CO LTD
    • WAKITA EIJI
    • E02D17/04E02D5/20
    • PROBLEM TO BE SOLVED: To provide a landslide protection wall and a construction method therefor improved in a cost and a construction period while solving a problem of vibration/noise by forming a slope face-like land slide protection wall by a ground improvement, restraining a construction site to a arrow range, simplifying a work process, and improving workability. SOLUTION: This landslide protection wall 2 is constituted by superposing landslide protection walls 2 by a ground improvement construction method in a multilayer shape on the excavating side, and heat part arrangement of the respective landslide protection walls 2 and the length of the landslide protection walls 2 are set in response to the earth pressure stress distribution of the ground. Then, in the construction method, the landslide protection wall is constructed by superposing landslide protection walls 2 by a ground improvement construction method in a multilayer shape on the excavating side, but after setting head part arrangement of the landslide protection walls 2 by dryly excavating the ground up to the prescribed depth in response to the earth pressure stress distribution of the ground, a ground improvement is started, and then, the landslide protection wall 2 is formed in the prescribed length.
    • 10. 发明专利
    • CONSTRUCTION FOR REUSE OF EXISTING FOUNDATION
    • JP2000154549A
    • 2000-06-06
    • JP33131098
    • 1998-11-20
    • SHIMIZU CONSTRUCTION CO LTD
    • WAKITA EIJI
    • E02D27/12
    • PROBLEM TO BE SOLVED: To provide construction method for reuse of existing foundations capable of mixedly-using existing and new piles under conditions of the load higher than a prescribed value not acting on the existing piles and no stress concentration. SOLUTION: An existing foundation consisting of an existing foundation slab 2 and an existing pile 1 are left, through-holes are formed at appropriate positions on the existing foundation slab 2 for construction of new piles 4, and a new foundation slab 7 is formed on the new piles 4. A slip layer 5 and an elastic body 6 are disposed between the existing foundation slab 2 and the new foundation slab 7. An existing ground wall 3 and the existing foundation slab 2 serve as alternative earth retaining, therefore the construction of new earth retaining is unnecessary in the execution of work. The number of the new piles 4 can be reduced because the existing piles 1 and new piles 4 are used mixedly, and the slip layer 5 and the elastic body 6 can prevent the application of horizontal force to the existing piles 1 if an earthquake occurs, thus it is possible to ensure safe design.