    • 4. 发明专利
    • POSITIONING JIG FOR STEEL FRAME COLUMN
    • JPH07109840A
    • 1995-04-25
    • JP25830693
    • 1993-10-15
    • HITACHI SHIPBUILDING ENG COOHBAYASHI CORP
    • KAWAHARA TAKANORIONO HIDEO
    • E04G21/16E04G21/18
    • PURPOSE:To make straightness of both members accurately coincide with each other at a time point of hanging work by fitting four L-shape positioning plates to upper edge corner angle parts of an existing hollow steel frame column having a rectangular cross section, and arranging rotatable guide rollers on upper surfaces of the plates. CONSTITUTION:Positioning jigs 2 are in advance arranged on an upper edge of an existing steel frame column 1. A hung steel frame column 1 is guided for approximate positioning and is hung down at a time point when a bottom corner angle part thereof abuts against an inner side than a radius of any of guide rollers 6. Next, while the guide roller 6 is rotated, an outside part of the steel frame column 1 is lowering-guided in the peripheral direction. In a final state, four corner angle parts abut against peripheral stnrfaces of all the guide rollers 6 for positioning and the column 1 is installed on an existing steel frame column 1. Accordingly, workhours from hanging to installation can be remarkably decreased without the use of labor and a mechanical means for position correction.
    • 9. 发明专利
    • Level bracing device
    • 水平保护装置
    • JP2006016101A
    • 2006-01-19
    • JP2004193079
    • 2004-06-30
    • Ohbayashi Corp株式会社大林組
    • ONO HIDEOIWAMI YOSHIAKI
    • B66C15/00B66C23/28
    • PROBLEM TO BE SOLVED: To provide a level bracing device capable of exerting a sufficient tremor isolating function by suppressing the change in the load applied to a tremor isolating device irrespective of the direction of the external force applied.
      SOLUTION: The level bracing device 1 is installed between a building 10 and the post 22 of a tower crane 20 used in constructing the building 10 for supporting the tower crane 20 in the horizontal direction, and is equipped with a frame 40 arranged in such a way as surrounding the post 22, a stay 60 to connect the frame 40 with the building 10, and a friction damper 50 interposed between the frame 40 and the post 22. The friction damper 50 connects the post 22 with each corner 40A of the frame 40 having approximately a square shape, wherein the angle θ of the damper sliding direction to one side member of the frame 40 is approximately 45°.
      COPYRIGHT: (C)2006,JPO&NCIPI
    • 要解决的问题:提供一种能够通过抑制施加到震动隔离装置的负载的变化而能够施加足够的震动隔离功能的液位支撑装置,而与所施加的外力的方向无关。 解决方案:水平支撑装置1安装在建筑物10和用于构造用于在水平方向上支撑塔式起重机20的建筑物10的塔式起重机20的柱22之间,并且配备有框架40,该框架40布置 以围绕柱22的方式,将框架40与建筑物10连接的撑杆60以及插入在框架40和柱22之间的摩擦阻尼器50.摩擦阻尼器50将柱22与每个角部40A连接 框架40具有大致正方形形状,其中阻尼器滑动方向与框架40的一个侧构件的角度θ大约为45°。 版权所有(C)2006,JPO&NCIPI
    • 10. 发明专利
    • Sheath material mounting device and sheath material mounting method
    • SHEATH材料安装装置和护套材料安装方法
    • JP2006009407A
    • 2006-01-12
    • JP2004187833
    • 2004-06-25
    • Ohbayashi Corp株式会社大林組
    • TAGAMI HIROMASAYAGI MASAKITAMURA ETSUNORIKITANO TADASHIMATSUI MASAHIROONO HIDEO
    • E04G21/16E04G3/28
    • PROBLEM TO BE SOLVED: To shorten an occupied time for a crane when a sheath material is mounted on the outer surface of a building skeleton.
      SOLUTION: This mounting device comprises a pair of lifting beams 3 formed by integrating a pair of lifting pieces 4 connected to a sling W to the upper part thereof, connection columns 5 suspended from the tip lower part of the lifting beams 3 and connected to brackets 26 fitted to the outer surface side upper floor surface of the skeleton 25 beforehand, leg parts 6 positioned at the rear of the connection columns, suspended to the lower part of the lifting beams 3, and installed on upper floor surface support materials, a trolley 7 using the lifting beams 3 as guides and supported to be longitudinally moved along the guides, a chain block 8 suspended from the trolley 7 and liftably suspending the sheath material 23, and a gondola-like working frame 9 connected to the trolley 7 and horizontally moving together with the movement of the trolley 7.
      COPYRIGHT: (C)2006,JPO&NCIPI
    • 要解决的问题:当护套材料安装在建筑骨架的外表面上时,缩短起重机的占用时间。 解决方案:该安装装置包括一对提升梁3,其通过将连接到吊索W的一对提升件4与其上部相结合而形成,连接柱5悬挂在提升梁3的末端下部和 预先安装在骨架25的外表面侧上部地板表面上的支架26,位于连接柱后部的悬挂在起重梁3的下部的脚部6,并安装在上部地板支撑材料 ,使用起重梁3作为导向并被支撑以沿着导向件纵向运动的手推车7,从手推车7悬挂并可升降地悬挂护套材料23的链条8和连接到手推车的缆车式工作框架9 7,并与手推车7的运动一起水平移动。版权所有(C)2006年,JPO&NCIPI