    • 2. 发明专利
    • Segment
    • 分割
    • JP2004076518A
    • 2004-03-11
    • JP2002241718
    • 2002-08-22
    • Fujimi Koken KkMaeda Corpフジミ工研株式会社前田建設工業株式会社
    • KONDO KAZUMASAMORI TAKAOMI
    • E21D11/14E21D11/04F16B1/02F16B5/10F16B37/10
    • PROBLEM TO BE SOLVED: To provide segments which contribute to minimization of manual fastening work and efficient connection thereof.
      SOLUTION: The plurality of segments which are connected together to constitute a structure, each have connecting surfaces a to be connected to the surface of the other segment, and one of the connecting surfaces a has a male joint 1 and the other connecting surface a has a female joint 2 to be connected to the male joint 1. The male joint 1 is protruded from the connecting surface and the female joint 2 is a hole into which the male joint 1 is fitted. Then a slipout preventing device and an elastic member are interposed into a fitting portion between the male joint 1 and the female joint 2. The slipout preventing device prevents slipout of the male joint 1 from the female joint 2. The elastic member is compressed when the male joint 1 is fitted into the female joint 2.
      COPYRIGHT: (C)2004,JPO
    • 要解决的问题:提供有助于最小化手动紧固工作和有效连接的部分。 解决方案:连接在一起以构成结构的多个段各自具有要连接到另一段的表面的连接表面a,并且一个连接表面a具有阳接头1,而另一个连接 表面a具有连接到阳接头1的阴接头2.阳接头1从连接表面突出,阴接头2是插入阳接头1的孔。 然后将防滑装置和弹性构件插入到阳接头1和阴接头2之间的配合部分中。防滑装置防止阳接头1从阴接头2滑出。当弹性构件被压缩时 男性接头1安装在女性接头2中。版权所有(C)2004,JPO
    • 3. 发明专利
    • Method of preventing collapse of working face in slurry shielding
    • 防止工业防护面料的剥离方法
    • JP2009243130A
    • 2009-10-22
    • JP2008090370
    • 2008-03-31
    • Maeda Corp前田建設工業株式会社
    • HIKITA TAKETOSHIKONDO KAZUMASAINOUE TAKU
    • E21D9/13
    • PROBLEM TO BE SOLVED: To provide a method of preventing the collapse of a working face in slurry shielding, which method accompanies a low risk of the collapse of a working face caused by slurry separation and power failure to keep the working face stable during a long period of suspension of shield propulsion. SOLUTION: In slurry shielding, slurry is supplied into a chamber 5 in front of a bulkhead disposed in a shield machine 1 to prevent the collapse of a working face 10 while drilling the working face 10 to propel the shield machine 1. When the propulsion of the shield machine 1 is suspended for a long period, slurry in the chamber 5 is replaced with gelled slurry prepared by mixing a gelling agent into slurry to prevent the collapse of the working face 10. COPYRIGHT: (C)2010,JPO&INPIT
    • 要解决的问题:为了提供防止浆料屏蔽中的工作面塌陷的方法,该方法伴随着由浆料分离和断电引起的工作面塌陷的风险低以保持工作面稳定 在长时间的悬挂盾构推进。 解决方案:在浆料屏蔽中,将浆料供给到设置在屏蔽机1中的隔板前面的室5中,以防止在钻孔工作面10的同时使工作面10塌陷以推进屏蔽机1。 屏蔽机1的推进被长时间悬挂,腔室5中的浆料被凝胶化的浆液所代替,该浆液通过将胶凝剂混合到浆料中而防止工作面10的塌陷。(C) 2010年,JPO&INPIT