    • 1. 发明专利
    • Construction method of screw pile
    • 螺丝桩施工方法
    • JP2006046067A
    • 2006-02-16
    • JP2005250645
    • 2005-08-31
    • Chiyoda Koei KkJfe Steel KkJfeスチール株式会社千代田工営株式会社
    • SHINOHARA TOSHIOSHIMAOKA HISATOSHIMORI GENHAYASHI MASAHIROOKAMOTO TAKASHIICHIKAWA KAZUOMI
    • E02D7/00E02D5/46E02D5/56E02D7/22
    • PROBLEM TO BE SOLVED: To provide a construction method of a screw pile for improving efficiency of screwing-in intrusion, reducing rotation torque greatly, and obtaining large tip supporting force and to provide the screw pile used in this method.
      SOLUTION: In this construction method for giving rotation force to a pile body 1 by a pile driving machine 30 by utilizing wood screw action of a blade 10 fixed substantially to a tip part of the hollow pile body 1 and ground digging action of an auger 20 and giving rotation force to a head part of the auger 20 to penetrate a pile into the ground by rotating it, a motor for rotating the pile and a motor for rotating the auger can rotate in the opposite directions to each other. When a tip part of the pile body 1 reaches a part close to a supporting layer, the auger 20 is inserted into the pile body 1 to give rotation force to the auger 20. A hardening fluid material is injected into the supporting layer from an auger head 22 while the pile body 1 rotates to stir and mix sediment and the hardening fluid material up to a predetermined depth, and then the pile body 1 is left and the auger 20 is pulled out to solidify sediment softened in accordance with elapse of time.
      COPYRIGHT: (C)2006,JPO&NCIPI
    • 要解决的问题:提供一种用于提高螺旋拧入效率的螺杆桩的施工方法,大大降低旋转扭矩,并获得大的尖端支撑力并提供该方法中使用的螺杆桩。 解决方案:在通过利用基本上固定在中空桩体1的前端部上的叶片10的木螺钉作用下由打桩机30向桩体1施加旋转力的施工方法中, 螺旋推运器20向螺旋推运器20的头部施加旋转力,以通过旋转钻头将桩穿入地面,用于旋转桩的马达和用于旋转螺旋钻的马达可以沿彼此相反的方向旋转。 当桩体1的尖端部分到达靠近支撑层的部分时,螺旋推运器20被插入桩体1中,以向螺旋推运器20提供旋转力。硬化流体材料从螺旋钻被注入支撑层 头部22,同时桩体1旋转以将沉淀物和硬化流体材料混合至预定深度,然后留下桩体1,并且将螺旋推运器20拉出以固化随着时间的流逝而软化的沉积物。 版权所有(C)2006,JPO&NCIPI
    • 3. 发明专利
    • Work execution method for screwed pile and screwed pile used therefor
    • 用于螺旋桩和螺旋桩的工作执行方法
    • JP2005048590A
    • 2005-02-24
    • JP2004332670
    • 2004-11-17
    • Jfe Steel KkJfeスチール株式会社
    • HAYASHI MASAHIROOKAMOTO TAKASHISHINOHARA TOSHIOMORI GEN
    • E02D5/56E02D5/72E02D7/00E02D7/22
    • PROBLEM TO BE SOLVED: To provide a work execution method for a screw pile and the screwed pile used therefor by which the efficiency of screwing-in penetration can be improved and the pile can be embedded by being screwed in up to a harder ground with a rotary torque greatly decreased, while a large end bearing capacity can be obtained by using a blade.
      SOLUTION: The work execution method is to install a hollow pile body 1 having a blade 10 at its tip or near the tip in the ground, in which an auger 20 is inserted in a pile body 1 so that its tip end is projected from the fore-end portion of the pile body 1 and then by giving a rotating force to the pile body 1 and the auger 20 in the mutually opposite directions the pile body 1 is screwed into the ground. When the pile body 1 reaches a specified depth, the auger 20 is pulled up.
      COPYRIGHT: (C)2005,JPO&NCIPI
    • 要解决的问题:为了提供一种用于螺丝桩的工作执行方法和用于其的螺纹桩,通过该工具可以提高螺纹穿透效率,并且可以通过拧入更硬的方式将桩嵌入 地面旋转力矩大大降低,而通过使用叶片可获得较大的端面承载能力。 解决方案:工作执行方法是在其顶端或靠近地面的尖端处安装具有叶片10的空心桩体1,其中将螺旋推运器20插入桩体1中,使得其顶端为 从桩体1的前端突出,然后通过在相对的方向上向桩体1和螺旋钻20施加旋转力,将桩体1拧入地面。 当桩体1达到规定的深度时,螺旋推运器20被拉起。 版权所有(C)2005,JPO&NCIPI
    • 4. 发明专利
    • THREADED TYPE STEEL PIPE PILE AND METHOD FOR CONSTRUCTING THE SAME
    • JP2001214440A
    • 2001-08-07
    • JP2001003206
    • 2001-01-11
    • NIPPON KOKAN KKCHIYODA KOEI KK
    • SHINOHARA TOSHIOMORI GENSHIMAOKA HISATOSHIHAYASHI MASAHIROOKAMOTO TAKASHI
    • E02D5/54E02D5/24E02D5/28E02D5/48E02D5/56E02D5/72
    • PROBLEM TO BE SOLVED: To obtain a threaded type steel pipe pile and method for constructing the pile as follows: (1) no vibration and no soil discharge work are possible to get, and application scope for threaded type steel pipe piles that can achieve bigger bearing end power is expanded up to larger diameter of steel pipe piles, (2) in relation to a base pile which is acted big horizontal force or bending moment from upper part work, head-enlarged steel pipe piles which can be designed economically, is made possible to be applied to threaded type steel pipe piles at low cost and without any difficulty in design and execution, (3) penetration resistance acted to an enlarged diameter section during construction work is little, as well as production cost for the enlarged diameter section is controlled low. SOLUTION: The threaded type steel pipe pile comprises a lower side steel pipe 2 which has wings 10 at least at the end or its vicinity, an upper side steel pipe 3 which has larger diameter than the lower side steel pipe 2, and a joint member 6 which connects the lower side steel pipe 2 and the upper side steel pipe 3. An outside diameter of the upper side steel pipe 3 is formed not bigger than an outside diameter of the wings 10, and an outside diameter of the joint member 6 is formed approximately the same with the outside diameter of the upper side steel pipe 3. The joint member 6 is made up of a circular steel plate or a doughnut- shaped steel plate that has an inside diameter smaller than an inside diameter of the lower side steel pipe 2, and is connected by welding to the bottom end of the upper side steel pipe 3 and to the top end of the lower side steel pipe 2.
    • 7. 发明专利
    • SCREWED TYPE STEEL PIPE PILE AND ITS EXECUTION METHOD
    • JP2000073365A
    • 2000-03-07
    • JP24219398
    • 1998-08-27
    • NIPPON KOKAN KKCHIYODA KOEI KK
    • SHINOHARA TOSHIOMORI GENSHIMAOKA HISATOSHIHAYASHI MASAHIROOKAMOTO TAKASHI
    • E02D5/56
    • PROBLEM TO BE SOLVED: To expand a screw type steel pipe pile in diameter and to improve its function and execution property by connecting a large-diameter upper steel pipe with a specific outer diameter size to the upper end of a lower steel pipe having vanes at the tip section. SOLUTION: An upper steel pipe 3 having the outer diameter 1.15-1.6 times the outer diameter of a lower steel pipe 2 and 60-90% of the outer diameter of vanes 10 is connected to the upper end of the lower steel pipe 2 provided with the vanes 10 at the tip to form a screwed type steel pipe pile 1. When the pile 1 is rotated and intruded into the ground, the sediment below the vanes 10 is moved to the outer periphery of the pile 1 and compressed, however the pile 1 is intruded without receiving large frictional resistance because the gap water pressure is increased immediately after stirring, then the shearing resistance of sediment is recovered by the recovery of the soil grain bonding strength and the reduction of gap water pressure, and the peripheral frictional force is increased. Or, the steel pipe 3 welded with an inverse truncated conical short tapered steel pipe may be welded to the driven steel pipe 2 at the site. Intrusion torque can be reduced, a pile head section can cope with large bending moment, and the bending stress and horizontal displacement quantity at the time of an earthquake can be suppressed.
    • 10. 发明专利
    • Construction method of temporary bridge and precast floor slab used for construction method
    • 用于施工方法的临时桥梁和预制地板施工方法
    • JP2014025337A
    • 2014-02-06
    • JP2013121396
    • 2013-06-10
    • Jfe Steel CorpJfeスチール株式会社
    • NAKANISHI KATSUYOSHIMURAKAMI TAKUYAOKAMOTO TAKASHI
    • E01D21/00E01D19/12
    • PROBLEM TO BE SOLVED: To provide a high-versatility construction method of a temporary bridge which allows an emergency vehicle to pass, in a short period without using any special equipment.SOLUTION: A construction method of a temporary bridge uses a steel main girder member 1. According to the construction method of the temporary bridge, a plurality of steel main girder members 7 with rails are prepared in each of which a rail member 3 is fixed to a web 1a of the steel main girder member 1, and horizontal girder mounting plates 5 are mounted at predetermined intervals. A pair of steel main girder members 7 with rails are disposed while being separated at predetermined intervals. A horizontal girder member 11 is joined through the horizontal girder mounting plate 5 to the steel main girder member 7 with the rail. Both end portions of a precast floor slab 24 in a width direction are placed on the rail member 3 of the steel main girder member 7 with the rail. The precast floor slab 24 is slid and installed successively in an axial direction of the steel main girder 7 with the rail, and a steel plate 25 is laid on the precast floor slab 24, so that a bridge face is constituted.
    • 要解决的问题:提供一种允许紧急车辆在短时间内不使用任何特殊设备的临时桥梁的高通用性施工方法。解决方案:临时桥梁的施工方法使用钢主梁构件 根据临时桥梁的施工方法,准备多个具有轨道的钢主梁构件7,每个钢主梁7中的轨道构件3固定到钢主梁1的腹板1a上,并且水平梁安装 板5以预定间隔安装。 一对具有轨道的钢主梁7被设置成以预定间隔分开。 水平梁11通过横梁安装板5与导轨连接在钢主梁7上。 预制地板24的宽度方向的两端部通过导轨配置在钢主梁7的轨道部件3上。 预制地板坯24通过钢轨在钢主梁7的轴向上依次滑动安装,在预制地板坯24上铺设钢板25,构成桥面。