    • 4. 发明授权
    • Roll surface restoration system and method
    • 卷面修复体系及方法
    • US5460023A
    • 1995-10-24
    • US102348
    • 1993-08-05
    • Vladimir B. Ginzburg
    • Vladimir B. Ginzburg
    • B21B28/04B21B45/08B21B28/02
    • B21B45/08B21B28/04
    • Method and apparatus for cleaning oxide scale from rolling mill rolls comprises a cleaning spray system including a fluid header juxtaposed to a mill work roll and an associated backup roll and a plurality of nozzles equidistantly spaced along the length of the header. High pressure cleaning water sprays, for which water is supplied by a descaling pump when not in use for descaling, are directed onto a work roll, and by rotation of the header, then directed onto the associated backup roll. The water sprays are directed against the rolls at an angle from 3.degree. to 10.degree. for optimum removal of oxide scale. For even restoration of the roll surface, the cleaning spray system periodically during the cleaning operation is shifted axially along the length of the rolls a distance about one-half the spacing between adjacent nozzles.
    • 用于从轧机辊中清除氧化皮的方法和设备包括清洁喷雾系统,其包括与轧机工作辊并置的流体集管和相关联的支承辊以及沿着集管的长度等间距分布的多个喷嘴。 高压清洗水喷雾器,当不用于除垢剂时由除垢泵供水,被引导到工作辊上,并且通过头部的旋转,然后被引导到相关联的支承辊上。 水喷雾以3°至10°的角度对准辊,以最佳地除去氧化皮。 为了均匀地恢复辊表面,在清洁操作期间周期性地清洁喷雾系统沿辊的长度轴向移动约相邻喷嘴间距的一半。
    • 5. 发明授权
    • Metal strip cooling system
    • 金属带冷却系统
    • US5390900A
    • 1995-02-21
    • US233260
    • 1994-04-26
    • Vladimir B. Ginzburg
    • Vladimir B. Ginzburg
    • B05C5/00B21B45/02C21D1/667C21D9/573C21D1/62
    • C21D9/573B05C5/005B21B45/0233C21D1/667
    • An apparatus and method for cooling a metal strip, the apparatus having a header that receives and directs a curtain of water across the strip, a water collector on one side of the curtain of water and a source of air on the opposite side of the curtain of water arranged to direct a flow of air across the curtain of water and divert water into the water collector. A deflector is arranged to interrupt at least a portion of the flow of air such that at least a portion of the wall of water contacts and cools the strip of metal. The flow of air is provided at a pressure of about 50 to 100 psi and, with the flow of air completely blocked by a deflector, the strip of metal is cooled completely across the width of the strip.
    • 一种用于冷却金属带的装置和方法,该装置具有接收并引导水帘横跨该条带的头部,该水幕一侧的集水器和该帘幕的相对侧上的空气源 的水被布置成引导空气流过水幕并将水转移到集水器中。 偏转器布置成中断至少一部分空气流,使得水壁的至少一部分接触并冷却金属条。 在大约50至100psi的压力下提供空气流,并且随着空气的流动被导流板完全阻挡,金属条被完全冷却穿过带的宽度。
    • 7. 发明授权
    • Continuous backpass rolling mill
    • 连续回流轧机
    • US4793169A
    • 1988-12-27
    • US879369
    • 1986-06-27
    • Vladimir B. Ginzburg
    • Vladimir B. Ginzburg
    • B21B1/02B21B1/42B21B1/46B21B37/24B21H1/18B21B31/20
    • B21B1/463B21B1/42B21H1/18B21B1/024B21B37/24Y10T29/49991
    • A method for hot rolling a continuously cast thin slab to form strip comprising the steps of: (a) subjecting a segment of predetermined length of the slab to a reduction pass in a first direction between a pair of work rolls; (b) retracting the segment in a direction opposite the first direction to the entrance side of the work rolls while accommodating the additional length of the segment produced by the reduction operation; (c) repeating steps (a) and (b) in sequence as necessary to finish the segment; and (d) consecutively subjecting the next contiguous portion of the slab to steps (a), (b) and (c) until the slab is finished along its entire length. Apparatus for practicing the method also is disclosed.
    • 一种用于热轧连续铸造的薄板坯以形成带材的方法,包括以下步骤:(a)使一段预定长度的板坯在一对工作辊之间沿第一方向进行压下通道; (b)在容纳由所述还原操作产生的所述片段的附加长度的同时,使所述片段沿与所述工作辊的入口侧相反的方向退回; (c)根据需要按顺序重复步骤(a)和(b)以完成该段; 和(d)连续地对板坯的下一个连续部分进行步骤(a),(b)和(c),直到板坯沿其整个长度完成。 还公开了用于实施该方法的装置。
    • 9. 发明授权
    • Rolling mill method
    • 轧机法
    • US4730475A
    • 1988-03-15
    • US860054
    • 1986-05-06
    • Vladimir B. Ginzburg
    • Vladimir B. Ginzburg
    • B21B1/02B21B13/14B21B27/02B21B31/18
    • B21B13/142B21B2001/028B21B2027/022B21B2269/14
    • A metal workpiece such as a slab is rolled into a desired width without requiring broadsiding. The system generally involves reducing a first portion along the width of the workpiece to a first thickness while creating a second portion along the width of the workpiece having a thickness greater than the first portion thickness and having a predetermined mass. Subsequently the second portion is reduced to establish a predetermined increase in the width of the workpiece and a decrease in the thickness of the workpiece to obtain a substantially uniform thickness along substantially the entire width of the workpiece. A preferred approach includes providing a pair of cooperating work rolls at least one of which has a generally cylindrical portion and at least one adjacent tapered portion. Initial reduction is effected by employing a pair of cooperating cylindrical central portions and at least one tapered portion. This provides a workpiece with a reduced portion and an enlarged portion. The workpiece subsequently may be rotated 180 degrees or side shifted and rolled between a generally cylindrical central portion and a second pair of tapered portions. Subsequently, further reduction may be effected solely between a pair of central portions. Relative axial movement of one work roll with respect to another may be employed in effecting sequential spreading of the workpiece.
    • 诸如板坯的金属工件被轧制成所需的宽度,而不需要宽幅化。 该系统通常涉及将沿着工件的宽度的第一部分减小到第一厚度,同时沿着工件的宽度产生具有大于第一部分厚度并具有预定质量的厚度的第二部分。 随后,减小第二部分以建立工件的宽度的预定增加和工件厚度的减小,以在工件的大致整个宽度上获得基本均匀的厚度。 优选的方法包括提供一对协作的工作辊,其中至少一个具有大致圆柱形部分和至少一个相邻的锥形部分。 通过采用一对配合的圆柱形中心部分和至少一个锥形部分实现初始还原。 这提供了具有减小部分和扩大部分的工件。 随后可以将工件旋转180度或侧向偏移并在大致圆柱形的中心部分和第二对锥形部分之间滚动。 随后,可以仅在一对中心部分之间进行进一步的减小。 可以采用一个工作辊相对于另一个的相对轴向运动来实现工件的顺序铺展。