会员体验
专利管家(专利管理)
工作空间(专利管理)
风险监控(情报监控)
数据分析(专利分析)
侵权分析(诉讼无效)
联系我们
交流群
官方交流:
QQ群: 891211   
微信请扫码    >>>
现在联系顾问~
热词
    • 6. 发明专利
    • UNDERGROUND SLUDGE STORAGE EQUIPMENT
    • JP2000140899A
    • 2000-05-23
    • JP33338798
    • 1998-11-10
    • PENTA OCEAN CONSTRUCTION
    • ONODA KOJI
    • C02F11/00C02F11/12
    • PROBLEM TO BE SOLVED: To continuously treat a large amount of mud by providing a plurality of sludge storage and dehydration beds and supplying sludge to one or more of the beds from mud suctioning facilities during the time when sludge stored in the rest of the beds is being settled and dehydrated. SOLUTION: In this equipment, mud suction facilities 2 are placed on the bottom of a river or lake 1 and sludge collected within the mud suction facilities 2 is transferred to a confluence pipe 5 through a sludge recovery pipe 3, with air from a compressor 4 and there, a part of drainage of the sludge is discharged with a water discharge device 6 and the residual sludge is accumulated in a storage facilities 7 formed underground. The storage facilities 7 comprise a tank that is divided into two vessels, i.e., left and right sludge storage/dehydration vessels 9 and 10 by a partition wall 8 and each of the sludge storage/dehydration vessels 9 and 10 consists of an upper sludge storage section and a lower drainage chamber 12, both of which are partitioned from each other by a dehydration bed plate 11. The sludge supplied from the confluence pipe 5 is stored in one of the two vessels 9 and 10, and while the settling, dehydration and discharge treatment of the sludge in this vessel 9 or 10 are performed, the sludge is stored in the other vessel 10 or 9. Thereafter, this operation is repeatedly performed.
    • 7. 发明专利
    • UNDERGROUND STRUCTURE-CONSTRUCTING CAISSON AND METHOD FOR JOINTING THE SAME
    • JP2000096572A
    • 2000-04-04
    • JP28355498
    • 1998-09-21
    • PENTA OCEAN CONSTRUCTION
    • ONODA KOJI
    • E02D23/00E02D23/08
    • PROBLEM TO BE SOLVED: To form a void space having the maximum size necessary for immersion joint between preceeding and following caissons, fill a tapered space between slopes on the end faces of side walls with mortar, cope with high earth and water pressure by a simple earth retaining wall so that working load from the outside is directly borne on caisson side walls and to reduce a construction cost and a construction period of time for that purpose. SOLUTION: This underground structure-constructing caisson is projected to the end faces on side walls 1 and 2 of the caisson in a V-shape having the top in a position rectified to a bedrock side. A proceeding caisson is immersed in the ground. Then, a steel plate 16 extending across the end face is mounted to the bedrock side of a following caisson having the same shape of the end face as that of the preceeding caisson, while interlocking the steel plate 16 with the bedrock side of the preceeding caisson so that it is adjacent to the preceeding caisson through a specific space 3, the following caisson is immersed in the ground, an inside frame is erected from the bedrock side in order to close the space 3 formed between the tops in a slope 13c on the end faces of the preceeding and following caisson side walls 1 and 2, mortar is placed in a space 18 formed between the outside slope of the end faces on the preceeding and following caisson side walls 1 and 2 and inside frame 17 of the bedrock, the preceeding and following caisson side walls 1 and 2 are connected with reinforcement 4 between the inside slopes of them, and joint concrete 20 is placed between the end faces of the preceeding and following caissons.
    • 8. 发明专利
    • Method for removing and restoring underground installation
    • 拆除和恢复地下安装的方法
    • JP2010112037A
    • 2010-05-20
    • JP2008284400
    • 2008-11-05
    • Penta Ocean Construction Co LtdUemura Giken Kogyo Kk五洋建設株式会社植村技研工業株式会社
    • MARUTA SHINICHIABE FUMITADAONODA KOJIYOKOYAMA HIROMI
    • E21D9/06E02B3/10
    • PROBLEM TO BE SOLVED: To improve constructibility by preventing a traffic hindrance from being caused by the interruption of an upper road and by dispensing with carrying-in/carrying-out and temporary placement of a large amount of sediment in removing an underground installation while a construction range is reduced without requiring construction of large-scale cofferdam revetment in embankment work.
      SOLUTION: The underground installation 2 is enclosed with a cylindrical body 8 having a cross section including the underground installation 2. The demolition of the underground installation 2 and the excavation and removal of the sediment are performed in the cylindrical body 8, while the cylindrical body 8 is advanced underground from a starting shaft 9. After the cylindrical body 8 reaches an arrival shaft 10, a void after the movement of the cylindrical body 8 is backfilled while the cylindrical body 8 is returned to the side of the starting shaft 9.
      COPYRIGHT: (C)2010,JPO&INPIT
    • 要解决的问题:通过防止交通阻碍由于上部道路的中断而导致交通阻塞,并通过分配携带/携带和临时放置大量沉积物来移除地下室来提高建筑性 施工范围缩短,而不需要在堤防工程中建设大型围堰护岸。

      解决方案:地下装置2由具有包括地下装置2的横截面的圆筒体8封闭。地下装置2的拆除和沉积物的挖掘和移除在圆柱体8中进行,同时 圆柱体8从起始轴9向地下进入。在圆柱体8到达轴10之后,圆筒体8移动后的空隙被回填,而圆柱体8返回到起始轴的一侧 9.版权所有(C)2010,JPO&INPIT