![一种先张法预制工字梁及其施工方法](/CN/2019/1/153/images/201910769187.jpg)
基本信息:
- 专利标题: 一种先张法预制工字梁及其施工方法
- 专利标题(英):Pre-tensioning method prefabricated I-shaped beam and construction method thereof
- 申请号:CN201910769187.4 申请日:2019-08-20
- 公开(公告)号:CN110524675A 公开(公告)日:2019-12-03
- 发明人: 刘刚亮 , 陈杰 , 王成皿 , 王中文 , 徐一鸣 , 陈榕锋 , 邓百洪 , 陈泰浩 , 周毅 , 雷尊贵 , 崔立川 , 赵亚党
- 申请人: 保利长大工程有限公司 , 中交公路规划设计院有限公司
- 申请人地址: 广东省广州市天河区广州大道中942号
- 专利权人: 保利长大工程有限公司,中交公路规划设计院有限公司
- 当前专利权人: 保利长大工程有限公司,中交公路规划设计院有限公司
- 当前专利权人地址: 广东省广州市天河区广州大道中942号
- 代理机构: 合肥正则元起专利代理事务所
- 代理人: 韩立峰
- 主分类号: B28B1/093
- IPC分类号: B28B1/093 ; B28B11/24 ; B28B23/04 ; E01D19/00 ; E01D21/00
The invention discloses a pre-tensioning method prefabricated I-shaped beam and a construction method thereof. The construction method comprises the steps of steel strand tensioning and releasing, steel reinforcement framework binding and hoisting, concrete pouring and maintenance and I-shaped beam form removal. According to the method, effective prestress is guaranteed by collecting and controlling the tensile stress of the steel strands, and the shrinkage creep model of the pre-tensioning method I-shaped beam is established according to the actual attributes of poured concrete and a water reducing agent, so that the construction scheme and the structural design are optimized; the prestress is transmitted according to the bonding force of the steel strand and the poured concrete; in the elastic stage of the whole structure, the prestress is transmitted into the concrete structure through a certain transmission length; meanwhile, the steel bundles formed by the steel strands are free of frictional resistance loss along the way in the prefabricating process, so that the engineering quality is guaranteed, and the problems that the overall structural strength of the I-shaped beam is greatly reduced due to the fact that the prestress friction of the post-tensioned prefabricated part is too large, the stress ribs are prone to retraction and the prestress loss is too large are solved.
公开/授权文献:
- CN110524675B 一种先张法预制工字梁及其施工方法 公开/授权日:2020-05-29
IPC结构图谱:
B | 作业;运输 |
--B28 | 加工水泥、黏土或石料 |
----B28B | 黏土或其他陶瓷成分、熔渣或含有水泥材料的混合物,例如灰浆的成型 |
------B28B1/00 | 由材料生产成型制品 |
--------B28B1/08 | .靠振动或振摇 |
----------B28B1/093 | ..靠直接作用于材料上的装置,如靠全部或局部浸入材料中的芯 |