基本信息:
- 专利标题: 一种风电火电切机策略协调优化方法
- 专利标题(英):Wind power-thermal power cutter strategy coordination optimization method
- 申请号:CN201410283066.6 申请日:2014-06-24
- 公开(公告)号:CN104113086A 公开(公告)日:2014-10-22
- 发明人: 唐晓骏 , 牛拴保 , 罗红梅 , 霍超 , 陈得治 , 李媛媛 , 李晓珺 , 吉平 , 陈湘 , 申旭辉
- 申请人: 国家电网公司 , 中国电力科学研究院 , 国家电网公司西北分部
- 申请人地址: 北京市西城区西长安街86号
- 专利权人: 国家电网公司,中国电力科学研究院,国家电网公司西北分部
- 当前专利权人: 国家电网公司,中国电力科学研究院,国家电网公司西北分部
- 当前专利权人地址: 北京市西城区西长安街86号
- 代理机构: 北京安博达知识产权代理有限公司
- 代理人: 徐国文
- 主分类号: H02J3/46
- IPC分类号: H02J3/46
The invention provides a wind power-thermal power cutter strategy coordination optimization method. The method comprises the following steps that: step one, when a fault occurrence of the system is monitored, calculation is started to obtain a transient energy function of a wind power-thermal-power bundling system after the fault so as to determine whether the system is unstable; if so, the step two is executed; and if not, the cutter measure is not taken; step two, according to transient energy functions of thermal power generating units, whether any thermal power generating unit itself is unstable is determined; if so, the thermal power generating unit that is unstable is cut off and then the step one is executed; and if not, the step three is executed; step three, on the basis of the delivery power scale of the wind power-thermal-power bundling system before the fault and the delivery capacity limit of the power transmission channel after the fault, the thermal power generating unit capacity needing to be cut off is calculated; and after the cutter operation is completed and operation returns to the step one. According to the method provided by the invention, secure and stable operation of the wind power-thermal-power bundling delivery energy base station after the fault can be effectively guaranteed; the cutter capacities of the wind power and the thermal power are distributed reasonably; the effect of lost power generation capacity minimization is realized; the favorable conditions are created for system recovery after the fault; and the security and economy of the system are improved.
公开/授权文献:
- CN104113086B 一种风电火电切机策略协调优化方法 公开/授权日:2016-08-17
IPC结构图谱:
H | 电学 |
--H02 | 发电、变电或配电 |
----H02J | 供电或配电的电路装置或系统;电能存储系统 |
------H02J3/00 | 交流干线或交流配电网络的电路装置 |
--------H02J3/38 | .由两个或两个以上发电机、变换器或变压器对1个网络并联馈电的装置 |
----------H02J3/46 | ..发电机、变换器或变压器之间输出分配的控制 |