基本信息:
- 专利标题: 主动支撑巷旁充填沿空留巷的方法
- 专利标题(英):Method for actively supporting lane side filling gob-side entry retaining
- 申请号:CN201310080715.8 申请日:2013-03-14
- 公开(公告)号:CN103161480A 公开(公告)日:2013-06-19
- 发明人: 杨培举 , 刘长友 , 鲁岩 , 张宁波 , 郭卫彬 , 路鑫
- 申请人: 中国矿业大学
- 申请人地址: 江苏省徐州市大学路1号中国矿业大学科研院
- 专利权人: 中国矿业大学
- 当前专利权人: 中国矿业大学
- 当前专利权人地址: 江苏省徐州市大学路1号中国矿业大学科研院
- 代理机构: 江苏圣典律师事务所
- 代理人: 程化铭
- 主分类号: E21D15/44
- IPC分类号: E21D15/44 ; E21D17/00 ; E21F15/00
The invention discloses a method for actively supporting a lane side filling gob-side entry retraining. Firstly, a lane interior support and an enforcing support are built on a reserved lane according to a sounding rock condition and a working face. On the back of the working face, nogs, gangues or blockworks and the like are adopted to build a lane side filling wall along the edge of a gob. High-strength and sealed filling bags are paved on the filling wall, and high-expanding materials or cement coagulation serous fluid added with a rapid hardening early strength agent is filled into the filling bags through a grouting pump. The enforcing support is dismounted after a top plate behind the working face is movably stabilized, the high-strength and sealed filling bags are enabled to be contacted tightly with the top plate, and active support force is formed to be exerted on the top plate. By means of the active support force provided for the lane side filing wall, the top cutting capacity of a lane side filling body is enhanced, initial deflection of the entry retaining top plate is reduced, the stability of the top plate is improved, the quality of the gob-side entry retaining is improved, and repair rate of the gob-side entry retaining is reduced. The method is simple, convenient to operate and good in effect.
公开/授权文献:
- CN103161480B 主动支撑巷旁充填沿空留巷的方法 公开/授权日:2015-12-09
IPC结构图谱:
E | 固定建筑物 |
--E21 | 土层或岩石的钻进;采矿 |
----E21D | 竖井;隧道;平硐;地下室 |
------E21D15/00 | 支柱;支架 |
--------E21D15/02 | .非伸缩性支柱 |
----------E21D15/44 | ..液压、气压或液压-气压支柱 |