基本信息:
- 专利标题: 一种用于提高双连拱隧道中隔墙顶部浇筑密实度的装置
- 专利标题(英):Device for improving pouring compactness of top of partition wall in double-arch tunnel
- 申请号:CN201821528665.X 申请日:2018-09-19
- 公开(公告)号:CN208966367U 公开(公告)日:2019-06-11
- 发明人: 杜雄伟 , 于大举 , 王斐 , 逯家贝 , 程福周
- 申请人: 中建三局基础设施建设投资有限公司 , 中建三局集团有限公司
- 申请人地址: 湖北省武汉市武昌区武珞路456号新时代商务中心主楼40层
- 专利权人: 中建三局基础设施建设投资有限公司,中建三局集团有限公司
- 当前专利权人: 中建三局基础设施建设投资有限公司,中建三局集团有限公司
- 当前专利权人地址: 湖北省武汉市武昌区武珞路456号新时代商务中心主楼40层
- 代理机构: 北京科亿知识产权代理事务所
- 代理人: 傅海鹏
- 主分类号: E21F17/103
- IPC分类号: E21F17/103 ; E21D11/10
The utility model discloses a device for improving the pouring compactness of the top of a partition wall in a double-arch tunnel. The device comprises a mid-partition vault end template, an exhaust pipe, a grouting pipe, a pipe bottom protection device and a PE breathable film, the mid-partition vault end formwork is arranged at the end of a mid-partition vault. wherein a grouting hole and an exhaust hole are formed in the middle partition wall, the exhaust pipe is pre-buried in the exhaust hole, the grouting pipe is inserted into the grouting hole reserved in the arch crown end template of the middle partition wall, a pipe bottom protection device is arranged at the bottom of the grouting pipe, and a PE breathable film is pasted to the top of the middle partition wall and can exhaust airat the far end of the grouting hole. When the device is used, the operation is simple; the method comprises the following steps: filling a gap between a mid-partition wall body and a middle pilot tunnel primary support by spraying concrete; the grouting machine is used for grouting the top of the mid-partition wall, air at the far end of a grouting opening is exhausted through the PE breathable film, concrete is prevented from generating a cavity, and the device is easy to manufacture, convenient to operate, low in cost and capable of effectively improving the grouting compactness of the vault of the mid-partition wall of the multi-arch tunnel.
IPC结构图谱:
E | 固定建筑物 |
--E21 | 土层或岩石的钻进;采矿 |
----E21F | 矿井或隧道中或其自身的安全装置,运输、充填、救护、通风或排水 |
------E21F17/00 | 在其他地方没有涉及到的用于矿井或隧道的方法或装置 |
--------E21F17/103 | .防火墙,例如,用于通风 |