- 专利标题: 一种富水地层地铁暗挖隧道机械化施工方法
- 专利标题(英):Water-rich stratum metro subsurface tunnel mechanized construction method
- 申请号:CN201910839138.3 申请日:2019-09-05
- 公开(公告)号:CN110529121A 公开(公告)日:2019-12-03
- 发明人: 张东 , 高琨 , 杜明山 , 辛亮 , 马晓龙 , 胡贤奎 , 黄小平 , 贺尚修 , 韩竹青 , 刘硕 , 王扩 , 王伟
- 申请人: 北京建工土木工程有限公司
- 申请人地址: 北京市朝阳区京顺东街6号院2号楼2层202
- 专利权人: 北京建工土木工程有限公司
- 当前专利权人: 北京建工土木工程有限公司
- 当前专利权人地址: 北京市朝阳区京顺东街6号院2号楼2层202
- 代理机构: 北京思海天达知识产权代理有限公司
- 代理人: 沈波
- 主分类号: E21D9/00
- IPC分类号: E21D9/00 ; E21D9/12 ; E21D11/10 ; E21D11/15
The invention discloses a water-rich stratum metro subsurface tunnel mechanized construction method. The method comprises the crank arm trolley grouting and water stopping stage, the excavating earlysupport linkage stage and the excavating double-rail slag transport stage. Before excavation, a tunnel face is provided with nets in a hanging mode and profile steel, concrete is sprayed so that the tunnel face can be sealed, a multi-directional deep hole grouting trolley is pulled to the working tunnel face, the posture of a crank arm is adjusted, thus, the crank arm conducts drilling and grouting on fixed points on the completely-sealed tunnel face so that soil on the side and the rear portion of the tunnel face can be reinforced; the multi-directional deep hole grouting trolley gets away from the tunnel face, a double-arm multifunctional heading machine is pulled to be located in front of the tunnel face, two arms are used for excavating soil and building a steel grating, and core soilis reserved; and excavated muck enters a muck rail conveying system through a crawler belt arranged in a machine, the muck is transported to a tunnel vertical shaft through a muck truck on rails, a bridge crane lifts the muck to a muck warehouse to be transported, and one cycle of construction is completed. Through the construction method, tunnel water gushing and tunnel mud gushing are effectively avoided, the high construction efficiency is achieved, the risk is greatly reduced, and the construction safety is ensured.
IPC结构图谱:
E | 固定建筑物 |
--E21 | 土层或岩石的钻进;采矿 |
----E21D | 竖井;隧道;平硐;地下室 |
------E21D9/00 | 衬砌或不衬砌的隧道或平硐;其掘进的方法或设备;隧道、平硐的设计布置 |