- 专利标题: 旋挖钻机遇空洞成孔成桩的简易方法
- 专利标题(英):Simple method for pore-forming and pile-forming after cavity encountering of rotary drilling rig
- 申请号:CN201910768974.7 申请日:2019-08-20
- 公开(公告)号:CN110512594A 公开(公告)日:2019-11-29
- 发明人: 何世鸣 , 李江 , 田震远 , 周与诚 , 陈辉 , 司呈庆 , 黄鑫峰 , 郝雨 , 郁河坤 , 贾城 , 洪伟 , 王海宁 , 刘志刚 , 梁成华 , 杜高恒 , 王建明 , 郭跃龙 , 陈鹏
- 申请人: 北京建材地质工程有限公司 , 中材地质工程勘查研究院有限公司 , 北京城建科技促进会
- 申请人地址: 北京市朝阳区望京西路甲50-1号卷石天地大厦A座4层
- 专利权人: 北京建材地质工程有限公司,中材地质工程勘查研究院有限公司,北京城建科技促进会
- 当前专利权人: 北京建材地质工程有限公司,中材地质工程勘查研究院有限公司,北京城建科技促进会
- 当前专利权人地址: 北京市朝阳区望京西路甲50-1号卷石天地大厦A座4层
- 代理机构: 北京一格知识产权代理事务所
- 代理人: 滑春生; 赵永伟
- 主分类号: E02D5/30
- IPC分类号: E02D5/30 ; E02D3/046
The invention discloses a simple method for pore-forming and pile-forming after a cavity encountering of a rotary drilling rig. The simple method comprises the steps that 1, a pile position is determined; 2, protective piles are correspondingly constructed outside the two ends of acavity in the construction area to block the two ends of the cavity; 3, pile holes separated from the protective pilesin the pile position are excavated, the protective pile holes at the end head are directly filled with excavated good soil, and compaction is conducted by filling the soil; 4, a method of hole separation construction is adopted, the pile holes of each pile in the construction area are firstly excavated to the cavity, the pile holes are filled with the good soil of the adjacent pile holes and compacted until full compaction is achieved; 5, the pile holes skip-excavated in the middle is excavated again, soil filling and compaction are conducted until the construction of all the pile holes is completed; and 6, from the middle of the construction area, a conventional technology is adopted to complete the pile-forming construction in all the construction areas. The simple method has the advantages that under the condition of almost no increase in cost and no increase in construction period, all the pile construction at the cavity is completed, and the economic, environmental-friendly and social benefits are significant.
公开/授权文献:
- CN110512594B 旋挖钻机遇空洞成孔成桩的简易方法 公开/授权日:2020-12-29
IPC结构图谱:
E | 固定建筑物 |
--E02 | 水利工程;基础;疏浚 |
----E02D | 基础;挖方;填方;地下或水下结构物 |
------E02D5/00 | 基础工程专用的板桩墙,桩或其他结构构件 |
--------E02D5/22 | .桩 |
----------E02D5/24 | ..预制桩 |
------------E02D5/30 | ...混凝土或钢筋混凝土制的或钢和混凝土混合制的 |