基本信息:
- 专利标题: 软岩大变形段隧道仰拱处理用长锚杆的施工方法
- 专利标题(英):Construction method of long anchor rods for inverted arch treatment of tunnel in soft rock large deformation section
- 申请号:CN201910630192.7 申请日:2019-07-12
- 公开(公告)号:CN110318793A 公开(公告)日:2019-10-11
- 发明人: 李五红 , 邸建玄 , 赵月生 , 刘晓亮
- 申请人: 中铁十二局集团有限公司 , 中铁十二局集团第二工程有限公司
- 申请人地址: 山西省太原市西矿街130号
- 专利权人: 中铁十二局集团有限公司,中铁十二局集团第二工程有限公司
- 当前专利权人: 中铁十二局集团有限公司,中铁十二局集团第二工程有限公司
- 当前专利权人地址: 山西省太原市西矿街130号
- 代理机构: 北京润平知识产权代理有限公司
- 代理人: 邝圆晖; 岳永先
- 主分类号: E21D20/02
- IPC分类号: E21D20/02 ; E21D21/00 ; E21D11/18
The invention provides a construction method of long anchor rods for inverted arch treatment of a tunnel in a soft rock large deformation section. The construction method comprises the following steps: (S1) marking a plurality of construction rings in the longitudinal direction of the tunnel at an inverted arch part in the tunnel at a first interval, and marking a plurality of construction pointson each construction ring at a first annular interval; (S2) laying the long anchor rods on the construction points of each construction ring of the tunnel; (S3) injecting mixed slurry into the long anchor rods; and (S4) after grouting of the long anchor rods is completed for a first time period, installing anchor backing plates and nuts at the exposed ends of the long anchor rods. According to theconstruction method provided by the invention, the long anchor rods are laid to the inverted arch part of the deformation section of the tunnel according to requirements, and the soil body of surrounding rock of the inverted arch part of the deformation section is reinforced by grouting the long anchor rods, so that the soil body of the surrounding rock of the inverted arch part of the deformation section of the tunnel is stabilized, and it is ensured that the soil body of the surrounding rock of the inverted arch part after subsequent construction of the inverted arch part of the deformationsection of the tunnel cannot be deformed any more.
IPC结构图谱:
E | 固定建筑物 |
--E21 | 土层或岩石的钻进;采矿 |
----E21D | 竖井;隧道;平硐;地下室 |
------E21D20/00 | 安装锚杆 |
--------E21D20/02 | .有灌浆装置的 |