- 专利标题: 一种暗挖地铁车站站内爆破施工方法
- 专利标题(英):Station internal blasting construction method for underground excavating subway station
- 申请号:CN201810075468.5 申请日:2018-01-26
- 公开(公告)号:CN108343456A 公开(公告)日:2018-07-31
- 发明人: 朱凡 , 张国庆 , 潘普国 , 仝培培 , 张晋东
- 申请人: 中铁四局集团有限公司
- 申请人地址: 安徽省合肥市望江东路96号
- 专利权人: 中铁四局集团有限公司
- 当前专利权人: 中铁四局集团有限公司
- 当前专利权人地址: 安徽省合肥市望江东路96号
- 代理机构: 兰州中科华西专利代理有限公司
- 代理人: 曹向东
- 主分类号: E21D13/02
- IPC分类号: E21D13/02
The invention relates to a station internal blasting construction method for underground excavating a subway station. The station internal blasting construction method comprises the following steps that earth in the station is divided into an upper earth and a lower earth, and the upper earth and the lower earth are correspondingly divided into a plurality of layers in the vertical direction; eachearth layer in the upper earth is excavated by vertical eye blasting in sequence; after the upper earth blasting is completed, a middle plate of a main structure is applied so that the bottom of theplate is 1.5-2 meters higher than the upper surface layer of the lower earth below the middle plate; and the uppermost earth layer in the lower earth is blasted by horizontal eye blasting and the other earth layers are excavated by vertical eye blasting in sequence, after blasting, follow-up station construction operations can be completed according to conventional methods. The station internal blasting construction method integrates the open and underground excavating and blasting construction technology, layered and segmented blasting is carried out on the earth in the station, and a corresponding blasting mode is adopted for different positions, the construction safety is ensured, time and labor are saved, the construction efficiency is greatly improved, and the influence of blasting construction on a finished product structure is effectively controlled. The station internal blasting construction method is suitable for foundation pit excavation construction with rock layers, reverseconstruction of station structures and tight construction period.
IPC结构图谱:
E | 固定建筑物 |
--E21 | 土层或岩石的钻进;采矿 |
----E21D | 竖井;隧道;平硐;地下室 |
------E21D13/00 | 大型地下硐室;及其建造的方法或设备 |
--------E21D13/02 | .方法 |