基本信息:
- 专利标题: 风积沙路基施工方法
- 申请号:CN201710258028.9 申请日:2017-04-19
- 公开(公告)号:CN107012755B 公开(公告)日:2019-06-04
- 发明人: 丁世跃 , 刘继文 , 杨太吉 , 罗小新 , 郭炜欣 , 袁义华 , 谭云亚 , 苟松 , 陆鑫 , 向凯 , 崔岳川 , 齐进广 , 邹明 , 李胜兴 , 易中平 , 杨维 , 夏旺 , 荆杰 , 郭冬冬 , 张少均 , 贾骏涛 , 樊小宾 , 郑雄伟 , 徐世龙 , 王凯
- 申请人: 中铁七局集团第四工程有限公司
- 申请人地址: 湖北省武汉市东湖开发区茅店山西路2号
- 专利权人: 中铁七局集团第四工程有限公司
- 当前专利权人: 中铁七局集团第四工程有限公司
- 当前专利权人地址: 湖北省武汉市东湖开发区茅店山西路2号
- 代理机构: 北京远大卓悦知识产权代理事务所
- 代理人: 胡茵梦
- 主分类号: E01C3/00
- IPC分类号: E01C3/00 ; E01C3/04 ; C09K17/40 ; C09K103/00
The invention provides an aeolian sand subgrade construction method. The method comprises the following steps that surveying and setting out are conducted; a base layer is laid; padding is loaded and unloaded; a reinforcing layer is laid; a reinforcing layer is laid on the surface of aeolian sand, wherein the reinforcing layer comprises limestone, polypropylene fibers, loose filling and the balance coal ash; tilling is conducted, specifically, watering is conducted on the reinforcing layer, and tilling is conducted on a subgrade multiple times in the length direction; riffle watering is conducted; rolling compaction is conducted through a bulldozer; rolling compaction is conducted through a road roller; compaction detection is conducted, specifically, the compaction coefficient Kof the compacted aeolian sand is detected in a sand filling mode or a water filling mode; and the step that padding is loaded and unloading to the step that compaction detection is conducted are conducted repeatedly until the subgrade reaches a design elevation, and construction is completed. According to the aeolian sand subgrade construction method provided by the invention, the reinforcing layer is laid on the aeolian sand, the reasonable rolling compaction mode is adopted, the strength of the vibrated and compacted subgrade meets design requirements, the compressive strength is high, the failure strain resistance and tension resistance of the subgrade are greatly improved, and the stability of the subgrade is improved.
公开/授权文献:
- CN107012755A 风积沙路基施工方法 公开/授权日:2017-08-04
IPC结构图谱:
E | 固定建筑物 |
--E01 | 道路、铁路或桥梁的建筑 |
----E01C | 道路、体育场或类似工程的修建或其铺面;修建和修复用的机械和附属工具 |
------E01C3/00 | 路面基础 |