基本信息:
- 专利标题: 一种高密度聚乙烯非压力管道水平定向钻进施工方法
- 申请号:CN201710181674.X 申请日:2017-03-24
- 公开(公告)号:CN106870819B 公开(公告)日:2017-12-26
- 发明人: 李慧莹 , 王辉
- 申请人: 广州市恒盛建设工程有限公司
- 申请人地址: 广东省广州市白云区北太路1633号广州民营科技园科盛路8号配套服务大楼B408—2房
- 专利权人: 广州市恒盛建设工程有限公司
- 当前专利权人: 广州市恒盛建设工程有限公司
- 当前专利权人地址: 广东省广州市白云区北太路1633号广州民营科技园科盛路8号配套服务大楼B408—2房
- 代理机构: 广州三环专利商标代理有限公司
- 代理人: 王会龙; 向敢
- 主分类号: F16L1/028
- IPC分类号: F16L1/028 ; F16L1/11 ; E21B7/04 ; E21B7/18 ; E21B7/28
The invention relates to the technical field of engineering construction, in particular to a horizontal directional drilling construction method for a high density polyethylene non-pressure pipeline. According to the method, underground pipeline detection is firstly carried out and comprises the steps of underground prospecting and ground measurement, detecting data are corrected, judged and comprehensively analyzed, and a detecting result is provided; according to the detecting result, a hole drilling track is determined, meanwhile, a directional guide drilling system is adopted for drilling a small-diameter guide hole according to the hole drilling track through electromagnetic wave signal transmission; and a large-diameter drill bit is connected to the end of a drilling rod in a replaced manner for repeated chambering, the to-be-paved pipeline is pulled into the specific position in the drilling hole while the last time of chambering is carried out, and pipeline paving construction is carried out. By means of the construction method, underground obstacles can be avoided in complex urban area construction, the pipeline can be paved in a non-excavation pipeline paving technology in some loose and broken stratums, and therefore the construction method plays an important role and has a great effect in city non-excavation construction.
公开/授权文献:
- CN106870819A 一种高密度聚乙烯非压力管道水平定向钻进施工方法 公开/授权日:2017-06-20
IPC结构图谱:
F | 机械工程;照明;加热;武器;爆破 |
--F16 | 工程元件或部件;为产生和保持机器或设备的有效运行的一般措施;一般绝热 |
----F16L | 管接头 |
------F16L1/00 | 铺设或回收管子;在水上或水下检修或连接管子 |
--------F16L1/024 | .在陆地上铺设或回收管子,例如在地面上 |
----------F16L1/028 | ..在地下 |