- 专利标题: 跨线连续梁拆除方法及拆除用支架
- 申请号:CN201610918643.3 申请日:2016-10-21
- 公开(公告)号:CN106638336B 公开(公告)日:2018-08-10
- 发明人: 李亚民 , 艾祖斌 , 陈钒 , 黄巍 , 卢超 , 高天 , 卓越 , 杨霁 , 蒋帆 , 朱向阳 , 袁野 , 李杰 , 何志兰 , 熊利 , 苏坤 , 黄深镜
- 申请人: 中国水利水电第八工程局有限公司
- 申请人地址: 湖南省长沙市天心区常青路8号
- 专利权人: 中国水利水电第八工程局有限公司
- 当前专利权人: 中国水利水电第八工程局有限公司
- 当前专利权人地址: 湖南省长沙市天心区常青路8号
- 代理机构: 湖南兆弘专利事务所
- 代理人: 陈晖; 张丽娟
- 主分类号: E01D24/00
- IPC分类号: E01D24/00
The invention discloses an over-line continuous beam removing method. The method comprises the following steps of 1 support erecting, 2 temporary pier beam padding, 3 transverse stripping, 4 blocking hanging and 5 support removing. The invention further discloses a support for removing in the method. The support comprises supporting pieces and hoops, the supporting pieces are arranged on bearing platforms on the peripheries of the bottoms of the corresponding piers and are parallel to the piers, the supporting pieces are clamped on the sides of the piers through the hoops, distribution beam groups are installed on the tops of the adjacent two supporting pieces in an overlapping mode, and a bearing support used for bearing the weight of a bridge when the bridge is removed is installed on the tops of the distribution beam groups. The method has the advantages of being safe, stable, environmentally friendly in construction and the like, and the support has the advantages of being convenient to operate, capable of reasonably utilizing the mechanics principle and high in construction efficiency.
公开/授权文献:
- CN106638336A 跨线连续梁拆除方法及拆除用支架 公开/授权日:2017-05-10