![一种梯级水电站自动发电控制方法](/CN/2013/1/87/images/201310438530.jpg)
基本信息:
- 专利标题: 一种梯级水电站自动发电控制方法
- 专利标题(英):Automatic power generation control method for cascade hydropower stations
- 申请号:CN201310438530.X 申请日:2013-09-24
- 公开(公告)号:CN103545817A 公开(公告)日:2014-01-29
- 发明人: 张庭 , 肖亮 , 邵春梅 , 李宏川 , 马仪成 , 李红 , 宁光文
- 申请人: 许继集团有限公司 , 许继电气股份有限公司 , 许昌许继软件技术有限公司
- 申请人地址: 河南省许昌市许继大道1298号
- 专利权人: 许继集团有限公司,许继电气股份有限公司,许昌许继软件技术有限公司
- 当前专利权人: 许继集团有限公司,许继电气股份有限公司,许昌许继软件技术有限公司
- 当前专利权人地址: 河南省许昌市许继大道1298号
- 代理机构: 郑州睿信知识产权代理有限公司
- 代理人: 胡泳棋
- 主分类号: H02J3/14
- IPC分类号: H02J3/14
The invention discloses an automatic power generation control method for cascade hydropower stations. The automatic power generation control method is characterized in that each cascade power station is controlled according to a given cascade output operating mode in dispatching and limiting cascade output. The automatic power generation control method includes steps of firstly, calculating the maximum output Nmaxk of an ith-stage power station, determining load distribution among the power stations, sequentially comparing a given dispatch output N with the maximum output of each of power stations at each stage from the upstream and the downstream and the value of Nmaxk, stopping judgment when the N is smaller than or equal to the Nmaxk, and determining load-distribution power stations as the power stations from the first to the kth stage; finally, calculating distribution output of the power stations according to the flow balance principle. Output requirements are met by operation of the least power stations, operating cost of the cascade power stations is reduced, and the upstream power stations are given preference to load distribution; load is distributed for the power stations at various stages in inverse proportion according to water consumption rate of the power stations, and after-distribution values are subjected to rationality verification; automation degree of high-cascade small serial hydropower stations can be improved, power generation benefits are increased, safety operation level of the power stations is improved, and labor intensity of operators is lowered.
公开/授权文献:
- CN103545817B 一种梯级水电站自动发电控制方法 公开/授权日:2015-07-29
IPC结构图谱:
H | 电学 |
--H02 | 发电、变电或配电 |
----H02J | 供电或配电的电路装置或系统;电能存储系统 |
------H02J3/00 | 交流干线或交流配电网络的电路装置 |
--------H02J3/12 | .用于通过改变网络负载的一个特性来调整交流网络中的电压的 |
----------H02J3/14 | ..用于把负载接入网络或从网络断开的,例如逐渐平衡的负载 |