基本信息:
- 专利标题: 一种冻土区桩基内外护筒施工方法
- 专利标题(英):Inner and outer pile casing construction method for frozen soil area pile foundation
- 申请号:CN201310366541.1 申请日:2013-08-21
- 公开(公告)号:CN103422499A 公开(公告)日:2013-12-04
- 发明人: 韩学文 , 靳义奎 , 梁来先 , 薛基富
- 申请人: 国家电网公司 , 青海省电力公司 , 青海送变电工程公司
- 申请人地址: 北京市西城区西长安街86号
- 专利权人: 国家电网公司,青海省电力公司,青海送变电工程公司
- 当前专利权人: 国家电网公司,青海省电力公司,青海送变电工程公司
- 当前专利权人地址: 北京市西城区西长安街86号
- 代理机构: 西宁工道知识产权代理事务所
- 代理人: 陈文福
- 主分类号: E02D5/68
- IPC分类号: E02D5/68
The invention relates to the technical field of the frozen soil cast-in-place pile foundation of a power transmission line, in particular to an inner and outer pile casing construction method for a frozen soil area pile foundation. The inner and outer pile casing construction method for the frozen soil area pile foundation is characterized in that the rotary drilling rig pore forming technology is adopted in a pile foundation pore forming stage for construction; in the digging and pouring process, the inner pile casing and the outer pile casing are cooperated to construct so as to achieve the effects of quick pile foundation pore forming and stable pit wall in the pouring process on the premise of reducing pit wall collapse; the outer pile casing is rolled by increasing 200mm on the basis of the basic diameter, the height is 3m, a reinforcing plate with the width of 200mm is respectively additionally arranged on each of two ends, and four eyeholes of phi 25mm are evenly dug; and the inner pile casing is processed according to the basic diameter, the height of the inner pile casing is determined according to the upper limit value of the frozen soil, and the inner pile casing is generally manufactured into a standard knot of 3m. According to the inner and outer pile casing construction method for the frozen soil area pile foundation, the problem of the warm season construction of the cast-in-place pile foundation of the multi-year frozen soil area is solved, and the disturbance to multi-year frozen soil is reduced, thereby being favorable for the environment protection. The construction quality and the work efficiency of the pile foundation are improved, and the engineering cost is reduced. The inner and outer pile casing construction method has a simple structure, is convenient and quick to use and is economical and practical, and the days for construction are reduced.
公开/授权文献:
- CN103422499B 一种冻土区桩基内外护筒施工方法 公开/授权日:2016-03-02
IPC结构图谱:
E | 固定建筑物 |
--E02 | 水利工程;基础;疏浚 |
----E02D | 基础;挖方;填方;地下或水下结构物 |
------E02D5/00 | 基础工程专用的板桩墙,桩或其他结构构件 |
--------E02D5/22 | .桩 |
----------E02D5/68 | ..构筑护壁用的 |